Client Catholic Education
Location Beaudesert
Our Role Road Rehabilitation, Carpark Design , Fire Services
Schedule 2017

Project Detail

ACS Engineers were engaged to provide civil design to rehabilitate the deteriorating driveway and car park. The design included allowance for a stop-drop-go bay to improve the functionality of the area when children are being picked up and dropped off at school. Upon commencement of construction, an old deteriorating fire main was found. This was replaced with a fire main which conforms with the current standards. ACS Engineers provided project supervision and also coordinated the testing required for the fire main to be commissioned in accordance with Australian Standards and Queensland Fire Service Requirements.